Why we at Goliath 61 first questioned the request for proposals — and what that reveals about retrofits
When a high-bay warehouse has been in operation for over 30 years, hardly anyone knows every detail of the old control system anymore. Nevertheless, it must continue to operate while the technology is being replaced. In LOGISTIK HEUTE (Issue 11/2026), Hermes Fulfilment described (In German, paywalled) how this is being achieved at the Haldensleben distribution center and why the concept for it was completely rethought during the planning phase. Here, we share our side of the story. Our VP Sales Swen Weidenhammer and our Project Lead Jörg Behrend explain how this shift came about, how we adapt to established systems, and why software is not a product for us, but a tool.
The Most Important Points at a Glance
- There’s no standard scenario for a retrofit. Whether a “big bang” or parallel operation is the right approach depends on the initial situation, with all its constraints
- For us, the first step in establishing a business relationship – before even considering a solution – is a thorough analysis of the circumstances, which is why we start by listening intently.
- At Goliath 61, we replaced the material flow computer to enable both technology partners to remove the old storage and retrieval machines and install new ones, while maintaining high availability of the entire system.
- The software is the tool Hermes and Stöcklin use to implement the equipment replacement aisle by aisle.
Goliath 61 at a Glance High-bay warehouse with 61 aisles, approximately 1.2 million storage locations, and a rack height of 27 m. Thirty-nine old stacker cranes and eight transfer cars are being replaced by 61 aisle-specific stacker cranes from the Stöcklin Group. We first replaced the material flow computer (MFR): In March 2025, the old MFR was replaced in a “big bang” upgrade. Since then, the new computer has been controlling both old and new equipment simultaneously. The project is scheduled to be completed in 2028.
The Interviewees


Swen Weidenhammer is our Vice President of Sales and oversaw the project from the bidding process through to contract award.
Jörg Behrend is our project lead and managed the IT project behind Goliath 61 in collaboration with Hermes Fulfilment.
What “Retrofit” Means to Us
What does “Retrofit” mean to us?
Swen Weidenhammer: The term comes from the renewal of technology. For us, retrofit means modernization, and modernization means migration. A migration is always a customized solution. There is no standard for it. Nor is there a rule that you must or must not do it via a “big bang” approach. It depends on the circumstances.
Jörg Behrend: In established systems, there is no one-size-fits-all standard. That’s exactly how it is with our project partners. The goal is to protect an existing logistics system with functioning processes as an investment and to transition parts of it into a more modern era. You won’t get very far with a one-size-fits-all approach. Our project partners want to modernize without down time, so operations need to be kept running. They operate on a three-shift schedule and have only small time windows on the weekends. If they can’t deliver, that’s the worst thing that can happen. That’s the key constraint in every decision.
How We Develop a Concept
Sherlock Holmes has Watson so that someone will ask: How did you do that? How do we develop a concept when there’s no standard?
Swen Weidenhammer: By studying the requirements and the request for proposal, if there is one. Then, with the help of intensive workshops, we develop an understanding of the challenges. In the process, we ask very detailed questions and seek to gather all the information. Drawing on our experience, we are then able to present a technical and financial estimate of the effort required. At the beginning, we don’t explain anything – we just listen.
Isn’t it risky in sales to contradict a client?
Swen Weidenhammer: We don’t do this out of a desire to contradict, but for the sake of the matter at hand. In doing so, we review and verify the request for proposal. A client will see that we’ve understood where the challenges in the project lie and how we can reduce the risk. Anyone who has already experienced the challenges of a software migration can follow our line of reasoning very quickly, even if it has little to do with the solution proposed in the request for proposal.
Jörg Behrend: For us, disagreeing means, above all, asking questions. We ask the Watson questions: What are you doing there? Why is that the case? How did you come to the conclusion that it can be solved that way? What do you gain from it? And then: What if things were different at this point? That’s how you guide the client. It’s a process you go through together – not a lecture.
Where do we look for risks in a project?
Swen Weidenhammer: Not in the 90 percent that go smoothly, but in the few percent that some people overlook. With a migration, there comes a point of no return. That’s when you need a reliable strategy and someone by your side who knows where to look. No checklist can replace that experience.
Goliath 61: Why the Concept Changed Course
Hermes already had a well-thought-out migration plan. What happened during the workshops?
Jörg Behrend: Hermes had put a lot of thought into it beforehand and even revised the plan once more during the bidding process. We held three workshops. In one of them, I said, “I don’t understand what you’re doing here.” We needed to understand how the client thinks, what’s important to them, how they arrived at this point, and what their vision for the technical solution was.
It became clear just how complex the planned approach was. Hermes wanted to gradually phase out and replace the old material flow computer in parallel with the new one. But there was no longer anyone to contact regarding the old computer. It was like trying to square the circle. In the end, I said, “Guys, let’s stop overcomplicating things. What if we completely replace the old computer before the first new device arrives?” That took a while. It resulted in something that wasn’t originally called for in the request for proposals.
Hermes asked: “Are you building software for old devices that, in the end, no one will need anymore?”
Swen Weidenhammer: My answer back then was a clear “Yes” – once all devices are brought online and functioning flawlessly, the “old world” can be shut down. Then the project is complete!
From that moment on, the Hermes project team understood what our concept was: We first create a tool, even if part of it will no longer be needed later on.
Software as a Tool
What does it mean to say that the software is a tool?
Swen Weidenhammer: For Hermes and Stöcklin, the material flow computer is a tool. They use it to bring the new devices into the warehouse aisle by aisle on weekends, without turning it into an IT project every time. We built the intelligence for this in advance. For us, the core of the project was completed after about a year and a half, even though the equipment replacement will continue for several more years.
Jörg Behrend: We remain part of the modernization process through maintenance and ongoing optimization. But now, new equipment just needs to be added to the system. The project partners can focus on the hardware.
Partnership: TUP, Stöcklin, and Hermes
We needed a partner for the hardware. How did the collaboration with Stöcklin come about?
Swen Weidenhammer: At first, this was a major challenge for me during the course of the project. For intralogistics technology providers, the proposal phase of a migration project involves high costs: workshops, travel, preliminary concepts, and proposals – all while the chances of winning the project are uncertain. After we had identified the project and were looking for a general contractor, I surveyed the market accordingly. The response was very muted. My connection with Stöcklin came about through a personal recommendation. There, too, there was initial skepticism as to whether our approach could even work.
It was important that we didn’t present ourselves to Hermes as separate hardware suppliers and IT service providers, but rather as a single team. Stöcklin understood this immediately, and the collaboration within this team was exceptionally good.
What role did Hermes itself play?
Jörg Behrend: A major one. There was a great deal of expertise on the client side. Barbara Schröder and Reshma Kasargod wanted to know every single detail. Barbara has known the Haldensleben site for decades and asked about even the smallest details: If a new staff door is installed at the back of the warehouse, she knows whether two or four keys will be provided for it. With a counterpart like that, the back-and-forth is effective. We learn from it ourselves as well. We gain practical experience through our project partners, and we bring a broader perspective from our many projects.
What Can Be Transferred
Can the approach used for Goliath 61 be applied to other projects?
Jörg Behrend: The approach, yes; the solution, no. At Hermes, we completely replaced the material flow computer in advance. At Bosch, we’re relying on parallel operation of the old and new systems with dynamic load balancing. These are two opposite approaches, and both were the right choice for their respective projects.
Swen Weidenhammer: Software is merely a means to an end. If the process isn’t sound, even the best software won’t help. Our software isn’t a product you buy and are then forced to adapt to. We view our software solutions as a tool that we’re constantly improving for our customers to enable them to transform their intralogistics.